Precautions for installation of zero sequence current transformer
Apr 05, 2023| 1. Problems in installation
(1) Zero-sequence current transformer'>The current transformer should be installed on the bottom plate of the switch cabinet, and should be fixed by a reliable bracket. However, some manufacturers or construction units install the zero-sequence current transformer'>current transformer on the bracket under the bottom plate of the switch cabinet, and even bind the zero-sequence current transformer'>current transformer on the cable, which violates the The principle of fully enclosed switchgear is neither safe nor dust-proof, let alone small animals, leaving many hidden dangers.
(2) After the cable terminal passes through the external zero-sequence current transformer'>current transformer, the relative position of the cable's metal shielded grounding wire and the external zero-sequence current transformer'>current transformer is incorrect. According to the "Beijing Electrical Engineering Installation Regulations", the metal sheath at the terminal of the three-core power cable must be well grounded; the copper shield of each phase of the plastic cable and the steel armor should be tin-welded with the ground wire (oil-impregnated paper insulated cable lead-clad and armored) The ground wire should be welded), when the cable passes through the zero-sequence current transformer'>current transformer, the cable metal sheath and the ground wire should be insulated from the ground, and the cable ground point (the welding point between the cable ground wire and the cable metal shield) is below the transformer , the ground wire should be directly grounded;
When the grounding point is above the transformer, the grounding wire should pass through the transformer for grounding. The grounding wire must be connected to the special grounding copper bar in the switch cabinet. The grounding wire must be copper stranded wire or tinned copper braided wire. The cross section of the grounding wire must be Meet the requirements of the regulations. During the inspection, it was found that some cable grounding wires should pass through the zero-sequence current transformer'>current transformer, and some cable grounding wires should not pass through the zero-sequence current transformer'>current transformer. Act right.
(3) Due to the relatively large cable terminal, the magnetic circuit of the current transformer'>current transformer is not closed. At present, the commonly used 10kV power cables are three-core XLPE cables. >The current transformer cannot be put on, and the zero-sequence current transformer is disassembled during the construction'>The current transformer interface, the cable is put on, but the interface is forgotten to be restored; some are restored, but the interface is not restored strictly; some terminals The separation of the first three cores is thicker than the zero-sequence current transformer'>current transformer's inner diameter and just stuck in the middle of the zero-sequence current transformer'>current transformer so that the zero-sequence current transformer'>current transformer interface cannot be restored to close, resulting in Zero-sequence current transformer'>The magnetic circuit of the current transformer is not closed and cannot work normally.
(4) The zero-sequence current transformer'>current transformer's secondary connection was opened during the cable construction, and it was not restored in time after the work was completed, causing the current transformer'>current transformer's secondary coil to open.
(5) The grounding end of the cable metal sheath grounding wire is not welded to the terminal, nor connected to the grounding copper bar in the switch cabinet, but is casually lapped on the bolts of the switch cabinet body.
2. Correct installation method
(1) It should be ensured that the zero-sequence current transformer is selected > the inner diameter of the current transformer is larger than the outer diameter of the cable terminal head;
(2) Try not to dismantle the zero-sequence current transformer'>current transformer during construction. If it must be dismantled, it must be restored to its original state after the work is completed;
(3) The grounding wire must be copper stranded wire or tinned copper braided wire, the cross-section of the grounding wire should not be less than 25mm2, the grounding end should be welded with a terminal, and the grounding wire and the zero-sequence current transformer'>current transformer should be properly handled The relative position of the grounding wire must be installed on the grounding copper bar;
(4) The zero-sequence protection system should be adjusted before power-on to ensure that the protection works normally.